Park Point Homeowner Updates

Update #11 May 2018

With over 100 PDI”s complete, we are thrilled with the quality of homes which are averaging only 1 minor cosmetic deficiency per unit. According to ANHWP, this could be a record for Alberta. More importantly, Homeowners have been absolutely thrilled!

By now all Homeowners would have received the Important Completion and Possession Information Notice that was sent this month. Please ensure that you read the document and complete the time sensitive lawyer information as soon as possible.

While the Purchase AgreementImportant Completion and Possession Information Notice, and QLU Homeowner Completion Guide all explain the process and restrictions regarding specific dates, we still receive many inquiries from Homeowners Requesting specific dates. As a reminder:

Qualex is busy registering the Condominium Plan at the Alberta Land Titles Office in order to be able to transfer title to your unit to you. Before a Condominium Plan can be registered, the City of Calgary must review and approve the final Condominium Plan and inspect the entire Project property. This step is beyond the control of Qualex, involves many parties, and can take some time; therefore, specific dates cannot be provided until all documentation is filed. We currently estimate that Closings and Possessions will commence (process will begin at a rate of about 8 units per day) in late July, 2018.

Regardless of any informal discussions about the Completion Date and Possession Date between you and the Sales Team or Homeowner Care, the Completion Date Notice and subsequent Possession Date will officially and formally specify the date for completing your purchase and the date when you can obtain keys to your unit – as per the agreed upon terms in your Purchase Agreement.

Please see your Purchase Agreement, Important Completion and Possession Information Notice or  QLU Homeowner Completion Guide for more information.

 

PP May 2018

Nearly Done!


Update #10 April 2018

PDI‘s have been underway for a week now and are going very well. Homeowners have been very impressed as the homes are looking fantastic!. Haven’t had your PDI yet? don’t worry, we will contact you directly once your home is ready for the PDI.

As a general reminder, be sure you check your email (and ensure our emails aren’t going to spam) as important and time sensitive communication will be sent via email and this update page regularly. Some things to expect in the coming months:

  1. Legal Representation Options: Preferred rates for Purchaser legal representation. As you know, at Closing, you will need an Alberta Legal representative (other than Denton’s LLP)
  2. Property Management Introduction
  3. Your Homeowner Portal login and password
  4. Official Closing Notices including Closing Date and Possession date and time
  5. Information on how to schedule your Move In.
Park Point Lobby almost ready for paint.

Park Point Lobby almost ready for paint.

We continue to estimate that Closings & Possession will commence on or around August 1, 2018 and finish around end of September 2018.. This is a early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined and for answers to many common questions. While closing is still a few months away, now is a great time to start speaking with your mortgage lender and to start preparations.

Until the next update….

Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update #9 March 2018

Dear Homeowner,

We currently estimate that Closings will start on or about August 1, 2018. This is a early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined and for answers to many common questions. While closing is still a few months away, now is a great time to start speaking with your mortgage lender and to start preparations.

unnamed (1)

Actual completed & staged Home at Park Point

Pre Delivery Inspections

Pre-Delivery Inspections will start April 2018 through August 2018. We will be contacting you once your home is ready to schedule your appointment. You will receive about two weeks notice for your PDI date and time.

The PDI is your opportunity to confirm that work on your new home is complete and satisfactory and to identify anything that may require further attention. The PDI takes place a few months or weeks in advance of your estimated Closing/Possession. An inspection and orientation of your new home will take about one hour.

The Purchaser(s) on contract (only), your Qualex Homeowner Care Representative, and Axiom Representative (builder) will review the home for defects and deficiencies.

Another very important purpose of the inspection is to orient you to your new home and all its features. This will include demonstrations of equipment and useful information on maintenance and upkeep. Failure to ensure proper maintenance can cause undesirable living conditions or possibly void the warranty.

Click here to read important information regards your PDI and PI.

Thinking of Renting or Selling?

Click here if you are interested in renting or selling

Thank you!

Many thanks for your patience during the construction period. We are so pleased with how Park Point has turned out and know you will be too. In the meantime, check your Park Point Homeowner Resources Page often for updates, and ensure you are on the way to getting yourself prepared for the big day!

Sincerely,

Qualex-Landmark™ Homeowner Care

Back To Park Point Homeowner Care

Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update #8 January 2018

Dear Homeowner,

We continue to estimate that Closings will start on or about August 31, 2018. This is a early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined.

Retail Occupant Announcement

We’re happy to announce the arrival of Loch Gallery : Loch Gallery specializes exclusively in Canadian and European historical works of significance and established contemporary artists with an emphasis on paintings and sculptures. Established in Winnipeg, Manitoba in 1972, the gallery has become an institution, representing many of the country’s most important living artists, while continuing to specialize in 19th and 20th century fine art in of fine art in Canada


Contract Changes and Mortgages

We kindly remind you that any changes to the individuals on the purchase agreement (adding individuals for mortgage purposes, or removing individuals) must be done at least 45 days in advance of the estimated completion date. Late requests cannot be facilitated and may result in a delayed closing. By getting your mortgage approved now, you can avoid potential issues financing closer to possession. Feel free to reach out to our preferred lenders – more information

Pre Delivery Inspection

In the few months leading up to closing, we will conduct a Pre Delivery Inspection of your Home with you. We will provide you with several updates in advance once we get closer. For more information- QLU Homeowner Completion Guide

Sincerely,

Qualex-Landmark™ Homeowner Care

Back To Park Point Homeowner Care

Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update #7 November 2017

Closings

We continue to estimate that Closings will start on or about August 31, 2018. This is a very early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined.

Changes to Mortgage Lending

By getting your mortgage approved now, you can avoid potential issues with qualifying in the new year and rest easy knowing that you won’t have trouble with mortgage financing closer to possession. Feel free to reach out to our preferred lenders – more information

Pre Delivery Inspection

In the few months leading up to closing, we will conduct a Pre Delivery Inspection of your Home with you. We will provide you with several updates in advance once we get closer. For more information- QLU Homeowner Completion Guide

Interiors looking great!

Interiors looking great!

 

IMG_0023

Exterior nearing completion

Back To Park Point Homeowner Care

Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update #6 August 17, 2017

With just about a year to go, we are currently pouring level 35 and have drywall installed in about half the tower. The Armony Cucine cabinetry has started arriving from Italy and is being installed on the lower levels.

Check out this spectacular drone footage of Park Point construction progress  – thanks to  “Construction Central” on YouTube .


We currently estimate that Closings will start on or about August 31, 2018. This is a very early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined.

Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update # 5 – May 4, 2017

In this photo update, Axiom workers are inspecting the suspended slab on level 21 before the concrete pour. The crane points to the beautiful Rockies rising in the background.

We currently estimate that Closings will start on or about August 31, 2018. This is a very early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined.

Capture

>>>Back To Park Point Homeowner Resources
Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update # 4 – March 30, 2017

Driving by the site at the corner of 2nd St. and 12th Ave, you will notice that Park Point’s glazing is being installed on the lower levels, while the concrete pour continues on level 17 and upward. It wont be long now until we see some of the beautiful Italian Armony Cucine kitchens arrive.

We currently estimate that Closings will start on or about August 31, 2018. This is a very early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined.

IMG_9107
 Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update # 3 – February 20, 2017

PP FEB

A recent concrete slab pour was completed on level 12. Park Point is now truly rising over the Beltline and Central Memorial Park.

We currently estimate that Closings will start on or about July 31, 2018. This is a very early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined.

 Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update # 2 – November 22, 2016

We are thrilled to announce that the last large concrete pour for Park Point has been completed over the weekend! Axiom Builders spent 13 hours on Saturday pouring approximately 1,300 cubic metres of concrete to complete Park Point’s 3rd floor podium slab.

Construction at Park Point is progressing with upwards of 75-100 workers on site daily, hitting every milestone in its advancement 34-storeys into the Calgary skyline. With the completion of this massive podium slab pour, Park Point construction will now advance by a floor a week until completion in 2018.

We greatly appreciate your purchase and help in making Park Point the next masterpiece in the Qualex-Landmark™ group’s award-winning Beltline Collection.

capture

We currently estimate that Closings will start on or about July 31, 2018. This is a very early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined.

 Qualex-Landmark™ is a licensed trademark, being used by Qualex-Landmark Union Inc. under license from Qualex-Landmark Management Inc. This document is for general reference and assistance purposes only. This document should not be relied upon as legal advice or as a substitute for maintenance guides, operational manuals, Condominium Property Act, bylaws or Warranty Program requirements.

Update # 1 – July 7, 2016

Dear Homeowner,

We currently estimate that Closings will start on or about July 31, 2018. This is a very early estimation for general reference purposes only. Please read your QLU Homeowner Completion Guide for further details on how the closing date is determined.

Whats happening below? Well, the hard working Axiom crews are currently working on Parking Level 3 of the underground parkade. As you can see, Park Point is starting to take its form!