Rendering of project. Credit: Qualex-Landmark

GREEN ON QUEENSBURY

Homeowner Updates 


 

Homeowner Update #13: May 2019

Building 1:

Exterior siding being installed/painted
Metal siding installation on-going
Planter walls being poured
Suite painting Level 2
Countertop install on Level 2
Flooring on Level 2
Finishing carpentry Level 1
Plumbing finishes on Level 1
Tile Install on Level 1
Electrical finishing on Level 1
Cabinet install on Level 1

Building 2:

Exterior siding installation has begun
Drywall on Level 4
Electrical rough in on Level 3
Plumbing rough in on Level 2

Building 3:

Windows installed
Mechanical rough-in on-going

Very Important:

 
All approved assignments and or contract name changes ( to add or remove buyer(s)) must be made no later than August 31, 2019. Due to the mandated Condo and Strata Assignment Integrity Register (CSAIR) for which we have no control, we are unable to make any extensions.

Please check with your lender as soon as possible to determine if you need to assign, add an individual(s) or remove an individual(s) to the Agreement for mortgage approval.

 
Please take the time to read our important and informative Homeowner Completion Guide  to ensure you are all prepped for the big day.”

 

Anticipated Completion: The Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about November 1, 2019 for buildings: 707 & 733 and January 1, 2020 for building: 747 and that the possession date for the Strata Lots (the “Possession Date”) shall be the day following the Closing Date. The order of closings and specific dates will be determined by the Vendor only, and are not necessarily floor by floor. Move-in scheduling information will be included in your Closing Notice.

Until the next update!

Your Green Homeowner Care Team

green@qualex.ca

« Homeowner Resources


 

Homeowner Update #12: April 2019

Building 1:

Exterior cladding being installed on South face
Metal siding work to begin soon
Plumbing fixture install on Level 3
Suite painting Level 3
Finishing carpentry Level 3
Counter top install on Level 2
Tile Install on Level 2
Cabinet install on Level 2
Electrical rough in on Level 1

Building 2:

Windows complete
Mechanical/Drywall/Insulation work on going on Level 4

Building 3:

Prepping for window installation
Back framing is still on-going

Very Important:
 
All approved assignments and or contract name changes ( to add or remove buyer(s)) must be made no later than August 31, 2019. Due to the mandated Condo and Strata Assignment Integrity Register (CSAIR) for which we have no control, we are unable to make any extensions.

 

Please check with your lender as soon as possible to determine if you need to assign, add an individual(s) or remove an individual(s) to the Agreement for mortgage approval.

 

 
Please take the time to read our important and informative Homeowner Completion Guide  to ensure you are all prepped for the big day.”
 
Anticipated Completion:The Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about :November 1, 2019 for buildings: 707 & 733 and January 1, 2020 for building: 747
and that the possession date for the Strata Lots (the “Possession Date”) shall be the day following the Closing Date. The order of closings and specific dates will be determined by the Vendor only, and are not necessarily floor by floor. Move-in scheduling information will be included in your Closing Notice.

Until the next update!

Your Green Homeowner Care Team

green@qualex.ca

« Homeowner Resources


 

Homeowner Update #11: March 2019

Building 1:

Exterior brick cladding and hardie siding continue to be installed.
Plumbing fixture install on Level 4
Counter top install on Level 3
Tile Install on Level 3
Cabinet install on Level 2

Building 2:

Windows 90% installed
Mechanical rough-in on Level 2

Building 3:

Back framing is ongoing
Sprinkler rough-in on Level 3
Concrete topping poured up to Level 2

The Vendor currently estimates but does not warrant or represent, that Closing Dates shall commence on or about :

707 & 733 – November 1, 2019

 747 –  January 1, 2020

Until the next update!

Your Green Homeowner Care Team

green@qualex.ca

« Homeowner Resources


 

Homeowner Update #10: February 2019

Green on Queensbury is progressing with Building 3 well on its way!

Building 1:

Exterior brick cladding and hardie siding continue to be installed.
Countertop install on Level 4
Cabinet and tile install on Level 3
Prime paint on Level 2
Electrical and drywall on Level 1

Building 2:

Windows being installed
Mechanical rough-in on Level 3

Building 3:

Back framing is nearing completion
Sprinkler rough-in on Level 4 being installed

 

Estimated completion:

The Vendor currently estimates but does not warrant or represent, that Closing Dates shall commence on or about :

707 & 733 – November 1, 2019

 747 –  January 1, 2020

Until the next update!

Your Green Homeowner Care Team

green@qualex.ca

« Homeowner Resources


 

Homeowner Update #9: January 2019

In 2019, we’ll start to see Green on Queensbury take shape so keep a close eye on our updates!

Building 1:

Exterior brick cladding and hardie siding, Cedar soffit, Planter walls install.
Cabinet install in progress on Level 4
Doors and finishing carpentry completed on Level 3
Drywall and electrical rough-in completed on Level 2
Mechanical rough-in completed on Level 1

Building 2:

Our team is currently working on waterproofing and electrical rough-in for building 2.

Building 3:

Framing is almost completed and we’re down to one crane!

Updated estimated completion:

The Vendor currently estimates but does not warrant or represent, that Closing Dates shall commence on or about :

November 1, 2019 for buildings: 707 & 733 and January 1, 2020 for building: 747

Moodyville Park Revitalization

timeline

 

 

 

 

 

City updated info here with a timeline graphic >

It’s never too late to be prepared for Closing.

We recommend Bookmarking Green Homeowner Care for easy access.

Have you changed your contact details since your purchase? If so, please send us a quick email and don’t forget to include your strata lot number (found on top page of your purchase agreement).

The order of closings will be determined by the Vendor and Builder, and are not necessarily floor by floor. We will provide you written notice of your actual closing date approximately 3-4 weeks in advance. We will not be able to give you a precise date until that time.

Until the next update!

Your Green Homeowner Care Team

green@qualex.ca

« Homeowner Resources



 

Homeowner Update #8: December 2018

Happy holidays! Construction for Green is progressing and we’re seeing some exciting new changes happening.

Building 1: Boarding from L4 down is currently on the way. Elevator installation has also started.

Building 2: Our team is currently working on waterproofing and electrical rough-in for building 2.

Building 3: Framing is almost completed and we’re down to one crane!

It’s never too late to be prepared for Closing.

While the Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about January 1, 2020, time will fly by! It is never too late to talk to your bank about mortgage pre-approval well in advance of closings. Being prepared financially will certainly reduce last minute stress when you receive your Closing Notice. With stricter lending policies and stress tests now in place, mortgage pre approval and approval may take more time. We have found that in some cases, banks  require additional individuals on title or as guarantors to the mortgage in order to be approved. As per the Purchase Agreement, any changes to individuals on the purchase agreement must be ammended at least 45 days in advance of the estimated closing date. Speak to your lender today!

Tips for Mortgage Pre-Approval/Approval

We recommend Bookmarking Green Homeowner Care for easy access.

Have you changed your contact details since your purchase? If so, please send us a quick email and don’t forget to include your strata lot number (found on top page of your purchase agreement).

The Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about January 1, 2020 and that the possession date for the Strata Lots (the “Possession Date”) shall be the day following the Closing Date. The order of closings will be determined by the Vendor and Builder, and are not necessarily floor by floor. We will provide you written notice of your actual closing date approximately 3-4 weeks in advance. We will not be able to give you a precise date until that time.

Until the next update!

Your Green Homeowner Care Team

green@qualex.ca

« Homeowner Resources


 

Homeowner Update #7: November 2018

Rainy season is here but Green on Queensbury is moving along with great progress being made!

Building 1: We are currently working to complete mechanical and electrical rough-ins. Windows are now installed and waterproofing is on its way.

Building 2: Framing is complete and windows are currently being installed.

Building 3: Framing is ongoing for Level 3.

It’s never too late to be prepared for Closing.

While the Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about January 1, 2020, time will fly by! It is never too late to talk to your bank about mortgage pre-approval well in advance of closings. Being prepared financially will certainly reduce last minute stress when you receive your Closing Notice. With stricter lending policies and stress tests now in place, mortgage pre approval and approval may take more time. We have found that in some cases, banks  require additional individuals on title or as guarantors to the mortgage in order to be approved. As per the Purchase Agreement, any changes to individuals on the purchase agreement must be ammended at least 45 days in advance of the estimated closing date. Speak to your lender today!

Tips for Mortgage Pre-Approval/Approval

We recommend Bookmarking Green Homeowner Care for easy access.

Have you changed your contact details since your purchase? If so, please send us a quick email and don’t forget to include your strata lot number (found on top page of your purchase agreement).

The Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about January 1, 2020 and that the possession date for the Strata Lots (the “Possession Date”) shall be the day following the Closing Date. The order of closings will be determined by the Vendor and Builder, and are not necessarily floor by floor. We will provide you written notice of your actual closing date approximately 3-4 weeks in advance. We will not be able to give you a precise date until that time.

Until the next update!

Your Green Homeowner Care Team

green@qualex.ca

« Homeowner Resources


 

Homeowner Update #6: October 2018

Progress continues at Green on Queensbury! We are mostly framed-out, roof membrane is being applied, and some windows have already been installed.  This is truly cosmopolitan living surrounded by beautiful parkland.

When it comes taking care of every detail so your home ownership experience is worry free, our Homeowner Care Team takes pride in ensuring that every step of the process is carefully executed.

Capture

It’s never too late to be prepared for Closing.

While the Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about January 1, 2020, time will fly by!. It is never too late to talk to your bank about mortgage pre-approval well in advance of closings. Being prepared financially will certainly reduce last minute stress when you receive your Closing Notice. With stricter lending policies and stress tests now in place, mortgage pre approval and approval may take more time. We have found that in some cases, banks  require additional individuals on title or as guarantors to the mortgage in order to be approved. As per the Purchase Agreement, any changes to individuals on the purchase agreement must be ammended at least 45 days in advance of the estimated closing date. Speak to your lender today!

Tips for Mortgage Pre-Approval/Approval

We recommend Bookmarking Green Homeowner Care for easy access.

Have you changed your contact details since your purchase? If so, please send us a quick email and don’t forget to include your strata lot number (found on top page of your purchase agreement).

The Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about January 1, 2020 and that the possession date for the Strata Lots (the “Possession Date”) shall be the day following the Closing Date. The order of closings will be determined by the Vendor and Builder, and are not necessarily floor by floor. We will provide you written notice of your actual closing date approximately 3-4 weeks in advance. We will not be able to give you a precise date until that time.

Until the next update!

Your Green Homeowner Care Team

green@qualex.ca

« Homeowner Resources


Homeowner Update #5: July 2018

Looking good Green! This parkfront gem is really starting to take shape! Construction is of course well underway, and we understand from the City that park revitalization will commence Summer 2019 and the City plans on having it complete in time for Homeowner Possessions.

Green

Some new menu items have been added to your Green Homeowner Care page. We recommend Bookmarking Green Homeowner Care for easy access.

Have you changed your contact details since your purchase? If so, please send us a quick email and don’t forget to include your strata lot number (found on top page of your purchase agreemetn).

The Vendor currently estimates, but does not warrant or represent, that Closing Dates shall commence on or about January 1, 2020 and that the possession date for the Strata Lots (the “Possession Date”) shall be the day following the Closing Date. The order of closings will be determined by the Vendor and Builder, and are not necessarily floor by floor. We will provide you written notice of your actual closing date approximately 3-4 weeks in advance. We will not be able to give you a precise date until that time.

Until the next update!

Your Green Homeowner Care Team

« Homeowner Resources


Homeowner Update #4: May 2018

Hard to believe that it has only be eight months since we first started selling Green on Queensbury. Today, construction is progressing very well, and we are thrilled to still on track for a early 2020 completion.

Gmain

Literally in the Park!

Upcoming deposit? please see Wiring Information for a quick and easy way to make your deposit.

Until the next update!

Your Green Homeowner Care Team

« Homeowner Resources


Homeowner Update #3: March 2018

2nd Amendment to Disclosure Statement: 

The Disclosure Statement has been amended a second time to reflect the new mailing address for the Vendor. Please download your copy.

Park Revitalization Update:

We understand that the City of North Vancouver expects to commence Moodyville Park Revitalization this June! We are very excited to see the park evolve and interface with Green.

Deposits: An easy, fast and secure way to pay your deposit. As a reminder, with third and final deposits upcoming for many Homeowners, and with our Discovery Centre closed we have an easy way for Homeowners to provide their deposit(s).

View Wiring Information

Construction Update:

The footprint of the buildings are starting to take shape, despite battling through some snowy days on site.

Mar cons


Homeowner Update #2: February 2018

Deposits: An easy, fast and secure way to pay your deposit.

With third and final deposits upcoming for many Homeowners, and with our Discovery Centre closed we have an easy way for Homeowners to provide their deposit(s).

The most popular and convenient way to provide your deposit is via wire transfer.

1. Just visit your bank on or before your deposit due date

2. Have your bank wire funds from your account to our lawyer (held in trust)

3. Once our lawyer receives funds, you will receive a deposit receipt!

Below is the information required for Purchasers who are sending funds by wire to DENTONS CANADA LLP’s account at the Bank of Montreal. Simply provide the wiring information to your bank.

View Wiring Information

Construction Update:

Construction is currently on track and moving along!

Feb Cons

 

 


Homeowner Update #1: December 2018

Capture

 

 

 

 

 

 

 

 

 

 

 

First Amendment to Disclosure Statement dated December 14, 2017.

Further to your receipt and acknowledgement of Green on Queensbury’s Disclosure Statement dated September 2017, please see the link below to download a copy of the First Amendment to Disclosure Statement dated December 14, 2017.

In accordance with the Real Estate Development Marketing Act (REDMA), this First Amendment was filed to bring to your attention the following three updates:

1. The City of North Vancouver has issued Building Permit # BLD 2017 – 10300 in respect of the Development,

2. the Developer has obtained a financing commitment for construction financing, and

3. the Developer has entered into a master deposit protection contract.

We strongly encourage you to read the complete document below and save a copy for your files.

Download Green on Queensbury Disclosure Statement and First Amendment

We are thrilled that construction is moving along swiftly, and we look forward to providing you with regular construction updates moving forward.

Warm regards & Happy Holidays,


The Current Estimated Construction Completion Date is early estimate of construction completion (not possession/closings), and should not, in anyway, be interpreted or quoted as a notice of closing. For more information regarding closing dates, please refer to your Green Purchase and Sale Agreement. As per your Purchase and Sale Agreement, final suite sizes may vary. The noted drawings are not precise and are for reference only. We strongly recommend that you wait until possession or orientation to take measurements for the purpose of ordering furniture to ensure a good fit.
In preparation of this site and its sub-parts, every effort has been made to offer the most current, correct, and clearly expressed information possible. Nevertheless, inadvertent errors in information may occur. In particular but without limiting anything here, Qualex-Landmark Northern Limited Partnership and Qualex-Landmark Northern GP LTD. disclaims any responsibility for typographical errors and accuracy of the information that may be contained on it’s web pages. The information and data included herein has been compiled by Qualex-Landmark Northern Limited Partnership and Qualex-Landmark Northern GP LTD. staff from a variety of sources, and are subject to change without notice to the User.Qualex-Landmark Northern Limited Partnership and Qualex-Landmark Northern GP LTD.makes no warranties or representations whatsoever regarding the quality, content, completeness, suitability, adequacy, sequence, accuracy, or timeliness of such information and data.